The Covid-19 pandemic has directly impacted Public-Private Partnership (PPP) projects worldwide. As a result of these impacts, many of the projects were renegotiated to assure favorable conditions for either the public, private, or both parties. Based on this context, this study seeks to unravel contractual mechanisms implemented or modified within the context of renegotiation processes caused by the Covid-19 pandemic in Colombia’s PPP toll road projects. Thus, this research aims to determine the impacts of the pandemic and the contractual strategies implemented in different renegotiation processes of PPP toll road projects. The mechanisms were analyzed at individual and cluster levels by implementing natural language processing (NLP) and social network analysis (SNA) procedures. These methodologies facilitated the analysis of multiple contractual mechanisms to identify the different impacts and common strategies between renegotiation processes. This research determined the main drivers and strategies to mitigate the effects of the Covid-19 pandemic on Colombia’s PPP projects, providing a methodology to enable contractual and renegotiation analysis. Overall, the renegotiation processes revealed that the pandemic had an economic and time-related impact, with differences between processes based on the renegotiation initiator or project phase at which the process arises.

NLP AND SNA FOR UNDERSTANDING RENEGOTIATIONS OF TOLL ROAD PPPs AMID THE COVID-19 PANDEMIC / Rojas, D.; Guevara, J.; Khallaf, R.; Salazar, J.; DE MARCO, A.; Castelblanco, G.. - 10:(2023). (Intervento presentato al convegno 12th International Structural Engineering and Construction Conference, ISEC-12 2023 tenutosi a usa nel 2023) [10.14455/ISEC.2023.10(1).LDR-04].

NLP AND SNA FOR UNDERSTANDING RENEGOTIATIONS OF TOLL ROAD PPPs AMID THE COVID-19 PANDEMIC

DE MARCO A.;
2023

Abstract

The Covid-19 pandemic has directly impacted Public-Private Partnership (PPP) projects worldwide. As a result of these impacts, many of the projects were renegotiated to assure favorable conditions for either the public, private, or both parties. Based on this context, this study seeks to unravel contractual mechanisms implemented or modified within the context of renegotiation processes caused by the Covid-19 pandemic in Colombia’s PPP toll road projects. Thus, this research aims to determine the impacts of the pandemic and the contractual strategies implemented in different renegotiation processes of PPP toll road projects. The mechanisms were analyzed at individual and cluster levels by implementing natural language processing (NLP) and social network analysis (SNA) procedures. These methodologies facilitated the analysis of multiple contractual mechanisms to identify the different impacts and common strategies between renegotiation processes. This research determined the main drivers and strategies to mitigate the effects of the Covid-19 pandemic on Colombia’s PPP projects, providing a methodology to enable contractual and renegotiation analysis. Overall, the renegotiation processes revealed that the pandemic had an economic and time-related impact, with differences between processes based on the renegotiation initiator or project phase at which the process arises.
File in questo prodotto:
Non ci sono file associati a questo prodotto.
Pubblicazioni consigliate

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/11583/2982492
 Attenzione

Attenzione! I dati visualizzati non sono stati sottoposti a validazione da parte dell'ateneo