The purpose of this study was the development of a simulation model to verify the logistic feasibility of the construction of a new regazification offshore terminal feeding a power plant located in Africa, subjected to a possible future doubling. In particular the model was used to test the proper supply of LNG (Liquefied Natural Gas) in the power plant real operating conditions and with particular reference to certain sizing configurations of vessels involved (dimensional range for tank buffer, shuttle ship size range). The model, taking into account sea conditions data available on site, extensively characterized during the oceanographic studies made, and with reference to defense works type realization and preliminary sizing (and specifically the breakwater dam and the its effect on the perturbation conditions in the proximity of the ship's mooring points) has assessed the risk of the power plant supply failure and the consequent lack of production (Unavailability of LNG or shut down). Moreover, the model estimated, for the scenarios simulated, the residence berthing times, the maximum frequency of unloading and the mooring / unmooring frequency reachable
A system dynamics approach for managing the LNG procurement for an offshore platform feeding a power plant / Briano, Enrico; Caballini, Claudia; Modula, Davide; Revetria, Roberto; Testa, Alessandro. - STAMPA. - (2010), pp. 259-269. (Intervento presentato al convegno 9th WSEAS International Conference on System Science and Simulation in Engineering, ICOSSSE'10 tenutosi a Iwate, jpn nel October 4-6, 2010).
A system dynamics approach for managing the LNG procurement for an offshore platform feeding a power plant
CABALLINI, CLAUDIA;
2010
Abstract
The purpose of this study was the development of a simulation model to verify the logistic feasibility of the construction of a new regazification offshore terminal feeding a power plant located in Africa, subjected to a possible future doubling. In particular the model was used to test the proper supply of LNG (Liquefied Natural Gas) in the power plant real operating conditions and with particular reference to certain sizing configurations of vessels involved (dimensional range for tank buffer, shuttle ship size range). The model, taking into account sea conditions data available on site, extensively characterized during the oceanographic studies made, and with reference to defense works type realization and preliminary sizing (and specifically the breakwater dam and the its effect on the perturbation conditions in the proximity of the ship's mooring points) has assessed the risk of the power plant supply failure and the consequent lack of production (Unavailability of LNG or shut down). Moreover, the model estimated, for the scenarios simulated, the residence berthing times, the maximum frequency of unloading and the mooring / unmooring frequency reachableFile | Dimensione | Formato | |
---|---|---|---|
2010A systemICOSSSE-40.pdf
non disponibili
Tipologia:
2a Post-print versione editoriale / Version of Record
Licenza:
Non Pubblico - Accesso privato/ristretto
Dimensione
791.51 kB
Formato
Adobe PDF
|
791.51 kB | Adobe PDF | Visualizza/Apri Richiedi una copia |