This paper describes an accident (explosion and natural gas fire) that occurred in Turin (Italy), in which power distribution cables, tramway network feeding cables and a gas pipe were involved. The described accident is particularly interesting because it occurred in the town centre and lasted several hours, producing a very high risk for the population. Fortunately, nobody was injured, but 120 people were evacuated for 24 h. The sequence of events is described, the involved facilities are examined and the physical processes which led to the different top events are discussed. Actually, starting from a modest event (600 V electric cable loss of insulation), which most likely lasted for months, the aforementioned accident was reached in a crescendo of domino effects. This sequence has been represented by an ISD in which the failure of the different protection systems is highlighted. These protection systems were mostly based upon the strict respect of procedures both in the installation and in the following maintenance of the different utilities. These aspects have been also briefly devised in the light of Italian and foreign regulations concerning the problem of the coexistence of buried utilities.

Large N.G. explosion and fire involving several buried utility networks / Piccinini, N; Tommasini, Riccardo; Pons, Enrico. - In: PROCESS SAFETY AND ENVIRONMENTAL PROTECTION. - ISSN 0957-5820. - STAMPA. - 87:2(2009), pp. 73-80. [10.1016/j.psep.2008.02.007]

Large N.G. explosion and fire involving several buried utility networks

Piccinini, N;Tommasini, Riccardo;Pons, Enrico
2009

Abstract

This paper describes an accident (explosion and natural gas fire) that occurred in Turin (Italy), in which power distribution cables, tramway network feeding cables and a gas pipe were involved. The described accident is particularly interesting because it occurred in the town centre and lasted several hours, producing a very high risk for the population. Fortunately, nobody was injured, but 120 people were evacuated for 24 h. The sequence of events is described, the involved facilities are examined and the physical processes which led to the different top events are discussed. Actually, starting from a modest event (600 V electric cable loss of insulation), which most likely lasted for months, the aforementioned accident was reached in a crescendo of domino effects. This sequence has been represented by an ISD in which the failure of the different protection systems is highlighted. These protection systems were mostly based upon the strict respect of procedures both in the installation and in the following maintenance of the different utilities. These aspects have been also briefly devised in the light of Italian and foreign regulations concerning the problem of the coexistence of buried utilities.
File in questo prodotto:
File Dimensione Formato  
articolo via po_free.pdf

accesso aperto

Descrizione: articolo postprint
Tipologia: 2. Post-print / Author's Accepted Manuscript
Licenza: Creative commons
Dimensione 335.91 kB
Formato Adobe PDF
335.91 kB Adobe PDF Visualizza/Apri
1-s2.0-S0957582008000608-main.pdf

non disponibili

Tipologia: 2a Post-print versione editoriale / Version of Record
Licenza: Non Pubblico - Accesso privato/ristretto
Dimensione 1.63 MB
Formato Adobe PDF
1.63 MB Adobe PDF   Visualizza/Apri   Richiedi una copia
Pubblicazioni consigliate

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/11583/2260555