The Earned Value Management (EVM) methodology provides an index-based Estimate at Completion (EAC) formula to forecast the final cost of an ongoing project. However, neither the EVM methodology nor the literature in cost forecasting considers the occurrence of risks and how the cost contingency reserve (CC) is used to mitigate them. This study proposes a risk-adjusted cost EAC methodology based on nonlinear regression that captures the CC spending profile and exploits it to improve the EAC forecasting performance. The CC spending profile reflects the preventive, neutral, or reactive risk management strategy (RMS) adopted, which dictates how the CC reserve is depleted throughout the project execution. The framework was tested on a dataset comprising 79 constructions and engineering projects to evaluate its performance across the projects’ early, mid, and late stages. Results show that the proposed methodology provides timely forecasts — mean absolute percentage error (MAPE) improves as the project progresses — and that a proactive RMS is the most reliable one in all stages, with MAPE values of 14.57%, 12.28%, and 11.42%, respectively.

Influence of cost contingency management on project estimates at completion / DE MARCO, Alberto; Narbaev, Timur; Ottaviani, FILIPPO MARIA; Vanhoucke, Mario. - In: THE INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT. - ISSN 1562-3599. - ELETTRONICO. - (2023), pp. 1-11. [10.1080/15623599.2023.2239487]

Influence of cost contingency management on project estimates at completion

De Marco Alberto;Narbaev Timur;Ottaviani Filippo Maria;
2023

Abstract

The Earned Value Management (EVM) methodology provides an index-based Estimate at Completion (EAC) formula to forecast the final cost of an ongoing project. However, neither the EVM methodology nor the literature in cost forecasting considers the occurrence of risks and how the cost contingency reserve (CC) is used to mitigate them. This study proposes a risk-adjusted cost EAC methodology based on nonlinear regression that captures the CC spending profile and exploits it to improve the EAC forecasting performance. The CC spending profile reflects the preventive, neutral, or reactive risk management strategy (RMS) adopted, which dictates how the CC reserve is depleted throughout the project execution. The framework was tested on a dataset comprising 79 constructions and engineering projects to evaluate its performance across the projects’ early, mid, and late stages. Results show that the proposed methodology provides timely forecasts — mean absolute percentage error (MAPE) improves as the project progresses — and that a proactive RMS is the most reliable one in all stages, with MAPE values of 14.57%, 12.28%, and 11.42%, respectively.
File in questo prodotto:
Non ci sono file associati a questo prodotto.
Pubblicazioni consigliate

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/11583/2981055
 Attenzione

Attenzione! I dati visualizzati non sono stati sottoposti a validazione da parte dell'ateneo