Tunnel boring machine (TBM) performance prediction is often a critical issue in the early stage of a tunnelling project, mainly due to the unpredictable nature of some important factors affecting the machine performance. In this regard, deterministic approaches are normally employed, providing results in terms of average values expected for the TBM performance. Stochastic approaches would offer improvement over deterministic methods, taking into account the parameter variability; however, their use is limited, since the level of information required is often not available. In this study, the data provided by the excavation of the Maddalena exploratory tunnel were used to predict the net and overall TBM performance for a 2.96 km section of the Mont Cenis base tunnel by using a stochastic approach. The preliminary design of the TBM cutterhead was carried out. A prediction model based on field penetration index, machine operating level and utilization factor was adopted. The variability of the parameters involved was analysed. A procedure to take into account the correlation between the input variables was described. The probability of occurrence of the outcomes was evaluated, and the total excavation time expected for the tunnel section analysed was calculated.

From Exploratory Tunnel to Base Tunnel: Hard Rock {TBM} Performance Prediction by Means of a Stochastic Approach / Rispoli, Andrea; Maria Ferrero, Anna; Cardu, Marilena. - In: ROCK MECHANICS AND ROCK ENGINEERING. - ISSN 0723-2632. - STAMPA. - 53:(2020), pp. 5473-5487. [10.1007/s00603-020-02226-9]

From Exploratory Tunnel to Base Tunnel: Hard Rock {TBM} Performance Prediction by Means of a Stochastic Approach

Marilena Cardu
2020

Abstract

Tunnel boring machine (TBM) performance prediction is often a critical issue in the early stage of a tunnelling project, mainly due to the unpredictable nature of some important factors affecting the machine performance. In this regard, deterministic approaches are normally employed, providing results in terms of average values expected for the TBM performance. Stochastic approaches would offer improvement over deterministic methods, taking into account the parameter variability; however, their use is limited, since the level of information required is often not available. In this study, the data provided by the excavation of the Maddalena exploratory tunnel were used to predict the net and overall TBM performance for a 2.96 km section of the Mont Cenis base tunnel by using a stochastic approach. The preliminary design of the TBM cutterhead was carried out. A prediction model based on field penetration index, machine operating level and utilization factor was adopted. The variability of the parameters involved was analysed. A procedure to take into account the correlation between the input variables was described. The probability of occurrence of the outcomes was evaluated, and the total excavation time expected for the tunnel section analysed was calculated.
File in questo prodotto:
File Dimensione Formato  
Rispoli2020_Article_FromExploratoryTunnelToBaseTun_published.pdf

accesso aperto

Tipologia: 2a Post-print versione editoriale / Version of Record
Licenza: PUBBLICO - Tutti i diritti riservati
Dimensione 4.47 MB
Formato Adobe PDF
4.47 MB Adobe PDF Visualizza/Apri
Pubblicazioni consigliate

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/11583/2842901